Bayliss Boatworks construction update: Bayliss 62' Seven

by Bayliss Boatworks 2 Nov 2020 06:23 PST

Seven (Bayliss 62') is getting close to her christening date! In October, our department supervisors gathered in the cockpit to depart on Seven's first sea trial. She performed beautifully, surpassing our expectations for speed, even before running gear finalizations.

After the sea trail, Seven moved back inside the make-ready bay where she received her red and blue boot stripes, along with blue bottom paint. In late October, she emerged from the make-ready bay in full paint. Soon, the outriggers will be installed, finalizing her exterior appearance.

Within the interior, everything from valances to galley floors are making their way into final top coat. All galley cabinetry has been installed, and the salon and dinette tops have been fabricated, soon to make their way into final finish as well.

Now nesting spaces for everything from liquor bottles to silverware are being installed by our Interior Carpentry Crew. Within the lower levels, the granite countertops have been installed in each of the two heads. Seven's "Calacatta do Brazil" granite galley countertops will be installed in early November.

On the flybridge, our Electrical Crew has installed all electronics within the console dashboard, from Garmin screens to MTU controls. Our Exterior Carpentry Crew installed rod holders within the starboard bench seat, and the freezer liner within the forward console bench seat was secured and wired.

In preparation for Seven's christening at the end of the month, our Mechanical Crew is final testing and proving all mechanical systems in the pump room. Stay tuned for photos of the finished machinery and interior spaces in our next update after her christening!

Read more about Seven here.

Related Articles

Bayliss 67' Overtime construction update
The planking process has been completed After receiving three layers of cold-molded okoume plywood on the bottom and two layers on the hull sides, the planking process for Overtime (Bayliss 67') has officially been completed with the placement of her "whiskey plank". Posted on 10 Feb
Bayliss 75' construction update
The interior is progressing quickly Our greatest note was the installation of her 1,150 gallon forward fuel tank by our mechanical crew. Once in place, the paint crew was able to complete fairing, painting and top coat inside the machine tunnel - forward sole installation is next! Posted on 6 Feb
Bayliss 72' Old Reliable construction update
It won't be long until the cockpit comes to life Old Reliable's (Bayliss 72') cockpit development continues as the coaming and coverboards receive glassing. Our exterior carpentry crew is beginning the teak deck, hand-picking boards for installation. It won't be long until the cockpit comes to life! Posted on 2 Feb
Bayliss 67' Overtime construction update
The hull jigs have been set into place and secured The last few weeks have been eventful in the hull shop for Overtime (Bayliss 67'). With the jig base together, the hull jigs were set into place and secured. Posted on 9 Dec 2020
Bayliss 75' construction update
Construction of the main engine room has gained momentum Bayliss 75' fairing continues on the outside of the hull as she sees more changes happening on the inside this month. Posted on 7 Dec 2020
Bayliss 72' Old Reliable construction update
Soon the Exterior Carpentry crew will glass and paint the lower mezzanine tops Old Reliable (Bayliss 72') continues it's mezzanine development with stainless refrigerator/freezer liners being installed, dry storage compartments being glassed and the switch/control panel installation in the ERC. Posted on 5 Dec 2020
Bayliss 62' Seven construction update
Seven is geared to fish efficiently as possible In late November, Bayliss Boatworks delivered its most recent build to its owners, the 62-foot Seven; the first owners to enjoy two BBW christenings. Posted on 3 Dec 2020
Bayliss 62' Seven construction update
On the home stretch with the Paint & Fair Crew hard at work Seven (Bayliss 62') is in the home stretch! In late August, she moved into our paint bay where she received final paint. Our Paint & Fair Crew began their work with the application of a custom-blended shade of Imron "Cool Blue" on Seven's hull. Posted on 3 Sep 2020
Salty Tiger - Bayliss 62' construction update
Set to be delivered this month While it's her custom transom artwork that has garnered the most attention, she also features a teak cockpit deck and coverboards, constructed from hand-selected teak boards. Posted on 6 Jul 2020
Blue View - Bayliss 78' construction update
A product of over 71,000 man hours and nearly 30 months of labor Blue View is powered with MTU M96L 16V engines, each with 2,600 horsepower. Her top speed was registered at over 44 knots at completion. This top end speed translates to a 37.5-knot cruise at 2150. Posted on 2 Jun 2020